Spec. Building
Baton Rouge, LA
General Contractor: Premier Design
Flatwork Contractor: Buchanan Concrete of the Carolinas
Approximately 25,000 CY of flatwork, tilt-up, and exterior paving. A
portable plant was set up on-site producing concrete at a rate of
150+ cu/yds per hour. Pour sizes range from 100 yds. per day to
2,000 yds. per day.
|
Proctor & Gamble Distribution Center
Lima, OH
General Contractor: James N. Gray - Jim Wilkerson
Concrete: Ahal Contracting
Approximately 50,000 CY flatwork and paving.
|
Whirlpool Distribution Center
Orlando, FL
General Contractor: Exxcel Project Management, Columbus, OH
Concrete: Ahrens Concrete, Iowa City, Iowa
Approximately 25,000 CY flatwork, tilt-up and exterior paving.
|
Solo Cup Distribution Center
Social Circle, GA
General Contractor: Clayco Construction, St. Louis, MO
Concrete: Ahrens Concrete, Iowa City, Iowa
A joint venture between Mark Twain Redi-Mix and Tucco Concrete of
Tucker, Georgia. In excess of 40,000 cubic yards of flatwork tilt-up
and exterior paving.
|
Walgreens
Anderson, SC
General Contractor: Korte
Flatwork: Ace Avant - Michael Somero
Approximately 60,000 CY. This was a fast track project and high
production rates were required. A portable plant was set up on site
producing concrete at a rate of approximately 200+ cu/yds per hour.
The flatwork pours ranged from 500 to 2,000 cu/yds per day.
|
Toyo Tire
White, GA
General Contractor: James N. Gray - Jim Wilkerson
Flatwork: Thesson Concrete
Approximately 40,000 CY. A portable plant was set up on site
producing concrete at a rate of approximately 200+ cu/yds per hour.
The flatwork pours ranged from 500 to 1,000 cu/yds per day.
|
Romark
Hazleton, PA
General Contractor: Whiting-Turner
Flatwork: WL Contracting - Tim Robinson
Approximately 28,000 Yds. Mark Twain Redi-Mix, Inc. set up a high
production portable plant on site to supply all concrete for this
project.
|
IKEA Furniture Warehouse - Phase I
Perryville, Maryland
General Contractor: James Gray Company, Lexington, KY - Jim
Wilkerson
Approximately 38,000 Cu. Yds. High production portable plant was set
up to supply all of the concrete for the project. The flatwork pours
ranged from 700 to 1,000 Cu. Yds. a day, with production rates of
150 CY per hour.
IKEA Furniture Warehouse - Phase II
Perryville, Maryland
General Contractor: James Gray Company, Lexington, KY - Jim
Wilkerson
Approximately 38,000 Cu. Yds. High production portable plant was set
up to supply all of the concrete for the project. The flatwork pours
ranged from 700 to 1,000 Cu. Yds. a day, with production rates of
150 CY per hour.
|
Ace Hardware
Petersburg, Virginia
General Contractor: James Gray Company, Lexington, KY
Flatwork: Ace/Avant, Archdale, NC
Approximately 800,000 sq. ft.
|
E-Toys
Blair, Virginia
General Contractor: Clayco Construction, St. Louis, MO
Flatwork: Great Southern Concrete Jonesboro, GA
Approximately 25,000 cu/yds. This was a fast track project and high
production rates were required. A portable plant was set up on site
producing concrete at a rate of approximately 200+ cu/yds per hour.
The flatwork pours ranged from 500 to 2,500 cu/yds per day.
|
True-Serve
Hagerstown, Maryland
General Contractor: Clayco Construction, St. Louis, MO
Flatwork: Vee Jay Cement, St. Louis, MO
Approximately 40,000 cu/yds. This was a fast track project and high
production rates were required. A portable plant was set up on site
producing concrete at a rate of approximately 200+ cu/yds per hour.
The flatwork pours ranged from 500 to 2,500 cu/yds per day.
|
Harcourt Brace
Troy, MO
Contractors: Fenix Construction (Tilt Up Walls)
Ahal Contracting (Floors)
Interior flatwork pours were completed in four pours of
approximately 500 cubic yards each. A laser screed was used and Mark
Twain Redi-Mix was asked to supply 100 plus cubic yards per hour.
|
American Cyanamid
Palmyra, MO
Contractors: Carl Nelson Company Burlington, Iowa (Tilt Up Walls)
Ahrens Concrete, Iowa City, Iowa (Interior Flatwork)
Mike Nelson Concrete (Paving)
200,000 square foot building with tilt up walls. Job site was
located approximately twelve miles from Mark Twain Redi-Mix's
Hannibal plant. 150 cubic yards per hour were needed on the floor
while the laser screed was being used. Trucks were brought in from
other plants and the yardage needed was supplied.
|
6th & Cherry Street Parking Structure
Columbia, MO
Contractors: Paric Corporation, St. Louis, MO
Vee Jay Cement, St. Louis, MO
Approximately 3500 cubic yards, 5000 PSI concrete with a three day
break of 3000 PSI was supplied. Trial mixes were produced to design
concrete to meet specifications.
|
Northeast Correctional Facility
Bowling Green, MO
Contractors: J.S. Alberici, St. Louis, MO
Vee Jay Cement St. Louis, MO
Approximately 10,000 cubic yards. Numerous large pours were made at
100 cubic yards per hour up to approximately 350 yards.
|
Pillsbury Warehouse
Hannibal, MO
Contractor: Ahal Concrete, St. Louis, MO
Large slab on grade pours for interior floors. A laser screed was
used by Ahal, Mark Twain Redi-Mix was asked to supply 150 plus cubic
yards per hour which was accomplished.
|
Wilson Trailer
Moberly, MO
Contractors: Mike Nelson Company, Burlington, Iowa
Ahrens Concrete Iowa City, Iowa
8000 cubic yard job, large pours made on the interior flatwork using
laser screed. 100 plus cubic yards per hour was supplied for
flatwork and paving.
|
Mississippi River Bridge
Hannibal, MO
Contractor: Edward Kraemer & Sons Plain, Wisconsin
Approximately 36,000 cubic yards. Largest pour was 2,600 cubic yards
continuous. Production rates exceeding 100 plus cubic yards per
hour.
|
Everlast
Moberly, MO
Contractor: Prost Builders Jefferson City, MO
300,000 square foot metal building. A laser screed was used to pour
the floor, pour sizes up to 450 cubic yards, Mark Twain Redi-Mix
supplied concrete at approximately 100 plus cubic yards per hour.
|
Heilig Meyers
Moberly, MO
Contractors: Carl A. Nelson Company, Burlington, Iowa
Ahrens Concrete, Iowa City, Iowa
Approximately 450,000 square feet tilt up building. Large pours were
made on the floor in the morning followed by pouring the tilt-up
walls in the afternoon. A portable plant was set up on site and
concrete was supplied to the job site at 100 plus cubic yards per
hour.
|
Hubbell Distribution Center
Centralia, MO
Contractor: Synercon Construction Company, Columbia, MO
Approximately 20,000 cubic yards in the project. Mark Twain Redi-Mix
set up a high production portable plant on site to supply all
concrete for the project.
|
|
|